This page contains a list of scheduled project events, and key milestones and deliverables.
In addition, we maintain the following prioritized lists of what we're working on this week, and what we plan to do next week:
Monday 8/7/95, 1:30 pm
Monthly project review.
Location:: main conference room.
Friday 8/18/95, 10:00 am
Project demonstration for senior management.
Location: engineering lab.
Q1 -- Feasibility study and working prototype of new system
Completed.
Summary report and Visual Basic prototype available.
Q3 -- Report on database connectivity options among competing products
2/3 done.
Projected completion: September 29th.
Q4 -- Release of version 3.2
On track.
Projected ship date: December 11th.